In NB Canada when we get LVL's (Trusses + Floor joists + LVL's) they come with a plan and the suggested way of install is to nail 4 spikes every 1 foot. So 3 sandwiched together for a load bear beam.
2025-02-02 20:44:20
0
90muzzy Dave/Maddog1986 :
Did you check your door height? No crips? Just a perfect fit?
2024-12-19 11:53:32
1
matthewiraci :
I started framing 2003. we were never allowed to gun nail lvl's together. always hamd nailed with 16d's
2024-12-20 17:32:02
11
MotorCityBadBoy :
as long as you have goal posts and a place to mount my spring, looks good to me
2024-12-19 11:57:51
0
Rainman :
Why not do this one by one . Standing it up instead of having to struggle trying to lift it up
2025-01-03 22:46:24
0
Gomerz :
It’s not good to put the garage header all the way on the top overtime it will bow
2024-12-21 17:05:06
0
user8508115653099 :
The LVL has printing on it for a reason, shows grade/design capacity, date of manufacture etc. should always be showing on the inside..
2025-01-14 15:21:26
0
hoffman21185 :
its called portal framing...and you really should stagger the nails not row them.
2024-12-19 10:47:13
0
Scooter Campbell :
always shoot your nails at an angle when you're making your header board. you wanted to have to be destroyed to come apart.
2025-01-17 01:38:12
0
Chris :
yup king studs directly support the head that would fail
2025-01-31 14:05:04
0
Vampire Alberta :
that would fail inspection in my area because of the compression. The beam has to be supported directly