Can one do the contract midway construction? I have started construction ground floor completed now I’m about to start the first floor..
2026-06-29 17:26:35
1
aali :
DLP is maximum 6months, only government projects go for 12months and retention is 10% at the beginning of the project and 5% after practical completion.
2026-07-01 03:35:08
1
MS :
12 months where? under which contract?. DLP Is 6months under JBC.
at Certified practical completion, 1/2 moeity of the retention is released to the contractor.The remaining half after DLP expires provided the contractor attend to defects within DLP If any.
Gather your facts right
2026-06-29 20:11:33
2
Morome01 :
👊🏾🌟🙏👍🏾👏
2026-06-30 02:30:38
0