@civilengineeringtip: "What is the maximum liquidated damages that the contractor has to pay?"

Engineer Tesfaye
Engineer Tesfaye
Open In TikTok:
Region: ET
Saturday 25 July 2026 14:22:40 GMT
12551
680
36
51

Music

Download

Comments

engrabas198
Eng Abas Hassen :
The contractor pays 0.1% per day of delay, but the total liquidated damages cannot exceed 10% of the contract price
2026-07-25 14:59:06
8
yes24195
ወልደ ማርቆስ :
<=10% of the contract price!
2026-07-25 18:27:39
0
wzhab12345
ዳስ ጣል :
10% of the toatal contract price is the maximum ld
2026-07-26 06:04:15
0
haris_h4
haris_h4 :
it just on paper in our country bc project will not delay we will give them extension of time 😅 for no reason
2026-07-25 21:14:12
1
marara1205
Mararaa. :
Most of the time MLD-is 7.5%
2026-07-25 22:36:17
0
leul.a.b.g
Leul A.B.G :
maximum penalty is for 100 days meaning 10% of the remaining work
2026-07-25 19:16:33
0
haileyesustamene
hailepa tam :
ቀመር፦ የአንድ ቀን ቅጣት = የቀረው ሥራ መጠን × 0.1% (ወይም 1/1000) ስሌት፦ 30,000,000 ብር × 0.001 = 30,000 (ሰላሳ ሺህ) ብር በየቀኑ ደረጃ 2: የ 10 ቀናት ጠቅላላ ቅጣት ማስላት (Total Penalty) ቀመር፦ ጠቅላላ ቅጣት = የአንድ ቀን ቅጣት × የዘገየባቸው ቀናት ስሌት፦ 30,000 ብር × 10 ቀናት = 300,000 (ሦስት መቶ ሺህ) ብር
2026-07-25 15:46:46
4
fillimonlemlem
fillimon :
depends on the ability of his claim expert 🤫
2026-07-25 19:01:09
1
user6746336393242
kefyalew kebede :
6%
2026-07-26 05:01:26
0
girma.yitayew
Girma Yitayew :
10%
2026-07-26 00:10:49
0
lammiijufaar
Engineer Lemi JB3 :
I think 10%
2026-07-25 20:22:25
0
danielabate59
Daniel abate :
max 10% of the contract price
2026-07-25 18:27:42
0
girmay.filmon
Some dots can’t be changed :
Up to 10% not more than 10%
2026-07-25 18:30:51
0
ethiofirstone1
Sardida Bale :
Ten percent
2026-07-25 15:34:23
0
user75125582395991
user7512558239599 :
ቀስ ብለሽ እደጊ ገና ወጣሑ ወጣሑ አትበል ይሔን የኮንትራት ውል ያለ የነበረ ነገር ነው ታዲያ LD ማለቂያው እስከ ሰንት ፐርሰንት ድረስ ነው መልስልኝ???
2026-07-25 18:33:38
0
menagebagn
Creator.Search.Insight :
0.1 %
2026-07-25 14:29:54
0
rememberwealldietomorrow
ኑራ ናስር :
ኳልኩሌት ምንድነው😁
2026-07-25 20:32:17
0
sisay.negese3
sis :
10% mebilx yelebatim
2026-07-25 19:12:58
0
user5031234480203
user5031234480203 :
10% of total contract price
2026-07-26 07:30:08
0
emathreezer
EMA3 :
ስለ performance Bond 95% ለደረሰ ፕሮጀክት እንዲሁም 10% LD ተቀጥቷል 5% ደግሞ 1 item ( AC air conditionor) አላቀረበም የዚህን ኮንትራክተር ፐርፎርማን መውረስ ትክክለኛ ነው??????
2026-07-25 18:27:09
0
tesfa351
Tesfa - civil works QS in eng :
accordingly 27.1.a from the remain amount not execoued work amount 0.01%
2026-07-25 18:24:56
0
user98544070924661
Chuchu@7 :
not excessed 10%
2026-07-25 18:01:12
0
deep.man66
Deep Man :
10% of z contract price
2026-07-25 17:43:12
0
hagos.user33
hagos33 :
10%
2026-07-25 17:32:09
0
faya.tolera
Faya Tolera :
be Payment mikniyat projectu ketegotatebetis???
2026-07-25 19:24:20
0
To see more videos from user @civilengineeringtip, please go to the Tikwm homepage.

Other Videos


About