I dont understand ooo
if the mason will finish the block work within 1 to 2 months
the plumber should be available always or
2026-08-24 10:31:59
6
ryan boniface :
No hahahaha building around pipes would make walls weaker lol
2026-08-24 18:25:55
3
M.LESS :
breaking my walls on this side I don't want to do that one installing the pipes alongside the missings is hard work let them finish first that hard work you're trying to avoid is exactly what a bigger problem when you start breaking a completed wall to install plumbing pipes you can weaken the block work and damage the wall design allows it the plumber should work alongside the Mason following the mechanical or plumbing drawings and instructions on the construction site don't just use the easiest method follow the right procedure because fixing a mistake later can cost far more than doing it correctly from the beginning
2026-08-23 09:03:42
2
Iyke Donatus :
The best way to do these plumbing work is to provide ducting along side
2026-08-23 06:36:44
1
Mohammad Electric ⚡💡 🇲🇶 :
i am an electric i just emergine if i was the plumber 🤣🤣
2026-08-23 03:39:00
2
BA CHILE,THE PLUMBER :
what if the leak comes after????🥰
2026-09-01 18:33:10
1
monday constant :
Can u pay for the cost?
2026-08-24 07:46:31
1
🇧🇲 J.MILLS 🇧🇲 :
if mason's were considerate and known their jobs we wouldn't halfto break their walls ..if you wantbplumbers working next to you mason's..PRICE JUST WENT UP!💯
2026-08-26 11:11:26
0
Adefalu Biodun :
can you pay for it
2026-08-23 15:21:31
0
lay_lay_lay_122521 :
This is a true fact, and for all of y’all who don’t understand, breaking the wall will create more issues in the future
2026-08-25 14:58:49
1
Eng.klint :
How do you get slope for WHC,, when the pipes are built within the wall
2026-08-23 12:28:38
1
Teabel :
you lgo pay for the time
2026-08-23 04:30:29
1
Eazi.Ride :
this suggestion is only for waste line.
2026-09-01 07:58:28
1
Isaac Quansah :
smart move of work is very smart move
2026-08-23 19:47:54
1
easyflowbrothers :
tell that to electricians ..plumbers always come after the whole mason is done because there will always be some adjustments against the plan.
2026-08-28 10:00:43
0
arcopeyh :
This makes the best sense
2026-08-23 16:33:00
1
PLUMBERCOMWATERENGLTD :
Papa its 0-0
2026-08-24 09:26:09
1
Ochen Daniel :
unless you cast the whole house
2026-08-24 02:42:12
1
Plat official01🇨🇦🇺🇸 :
Will you pay for that
2026-08-23 04:39:25
1
Jamgoen ཡེ་ཤེས་རྡོ་རྗེ། FL8 :
That I should say it will be more complicated actually 🥰
2026-08-23 03:55:56
1
M.LESS :
time for you to lay your pipes alongside the block work no problem engineer let me finish first after everything I'll come and install my pipes and you start breaking the walls no plumber you're not breaking my walls on this site engineer I don't want to do that one installing the pipes alongside the missing is hard work let them finish first that hard work you're trying to avoid is exactly what can create a bigger problem when you stop breaking a completed works and damage the wall
2026-08-23 09:06:55
3
PADDIZ PLUMBING SERVICES 🚰 :
ducting system is the best way to go🥰🥰
2026-08-23 07:09:50
2
Sengwayo plumbing and project :
I disagree For safety reasons and common sense.
2026-08-23 17:36:23
1
To see more videos from user @ohiofa_1, please go to the Tikwm