@buildwithato: #creatorsearchinsights #buildingengineer Our thoughts and prayers are with the building owner, the artisans, engineers, and all the professionals involved in this project. 🙏🏾 We sincerely sympathize with everyone affected by this unfortunate incident and pray for a speedy recovery and restoration. May God provide the owner with the strength and financial means to rebuild and replace everything that has been lost. Let’s also remember that we are not here to judge or blame anyone. Construction mistakes and unforeseen incidents can happen on site, and what matters is learning from them and doing better. Let’s show them love, support, and encouragement during this difficult time. ❤️🏗️#creatorsearchinsights #builderconstruction #ConstructionGhana

buildwithato
buildwithato
Open In TikTok:
Region: GH
Thursday 24 September 2026 14:04:06 GMT
5288
126
25
20

Music

Download

Comments

caoimhin
Eidolon :
Is from design, just look at the span no beams or columns. I believe they were trying one way slab but got it wrong
2026-09-25 08:13:11
1
stephenakorsu0
stephenakorsu906 :
The problem is from the control of the concrete pressure that is coming from the pump Technician must be available before the operation.
2026-09-25 13:03:43
0
ing.kane
Mr.Kane | Civil Engineer 👷‍♂️ :
Cutting corners 😂it’s sad tho
2026-09-25 13:50:24
0
ny73831
NY :
Eiiiiii….3ka paaaa nie
2026-09-25 07:05:18
1
prophet.dan4
Prophet Dan :
Hmmm 🧐
2026-09-24 20:03:47
0
the_internet_guy3
The_INTERNET_guy :
he went for cheap labor
2026-09-24 23:34:16
2
brightcoloursimpr
bright colours impressions :
@The Real Estate Egghead seee
2026-09-24 22:14:42
0
k.c.works
K.C. WORKS :
1. The most common cause during casting: Formwork / Falsework failure - CONTRACTOR'S fault Over 80% of failures during casting are collapse of the formwork that holds the slab. If that is the cause, responsibility falls on: a) The Main Contractor / Site Engineer: • Using undersized props, timber instead of steel props, props not braced, props standing on soft ground • Removing props too early from floor below • Overloading - heaping concrete in one spot, parking a concrete pump on the slab, storing blocks on freshly cast slab • Pouring too fast, or too thick slab than designed • Not providing a competent carpenter/foreman to check levels and bracing b) The Formwork Carpenter / Scaffolder: Directly liable for poor erection, but legally his employer - the contractor - carries the liability. This is why the contractor carries insurance for temporary works. 2. If the failure is structural - Reinforcement or Design issue a) Structural Engineer is blamed if: • Slab thickness, steel size/spacing, or span was inadequate on the drawings • No checks for punching shear, deflection, or continuity • Drawings were not detailed enough for site to interpret • He approved a dangerous change on site b) Contractor / Steel Bender is blamed if: • They did not follow the drawings - wrong bar diameter, wider spacing to save steel, insufficient laps, chairs/spacers not used so steel sank to the bottom • They used rusty, reused, or lower-grade steel (e.g. using mild steel instead of high-yield) • Concrete cover was not maintained During casting, if steel has sunk because there were no concrete spacer blocks, the slab will crack and sag immediately under its own weight even if the design was correct. That is a workmanship failure.
2026-09-25 10:07:36
0
To see more videos from user @buildwithato, please go to the Tikwm homepage.

Other Videos


About