As a sparky, this was your most spot on video yet. Love it. Keepem coming
2026-10-02 23:28:10
13
happy bearded man :
check your mech electrical drawing, everything is ok
2026-10-03 02:13:21
0
Cody B. :
Replace plumber with low volt tech and it’s a replay of last week… Turns out the low volt tech they kept kicking down the road is in charge of fire alarm. Good luck with that final since they instructed me to just cover the holes…
2026-10-03 02:24:08
0
Chrisc :
didn't the electrician look at the submittal sounds like a he problem
2026-10-03 01:14:06
1
j_meski :
This problem is more common then it should be
2026-10-03 00:42:41
1
JC :
VAVs are 24 volts from a 500va transformer. easy money
2026-10-02 22:13:39
2
Sparky562 :
It’s called a coordination study lol
2026-10-03 01:19:45
0
Kollosus :
Where are you that HVAC doesn't work for the Mechanical?
2026-10-02 21:08:55
5
jeffm :
I've been to a site where they ordered dozens of high end hvac equipment as 3ph 460V for a building that was getting 3ph 230v. that was a rough start up when I pointed it out.
2026-10-02 23:31:36
8
1188141 :
Good luck if your GC doesn’t have an MEP specific PM 😂😂😂😂. No one ever coordinates MEP’s correctly
2026-10-03 00:04:26
0
Memhoe :
Somebody needs to get fired
2026-10-02 23:18:53
0
Will Broughton775 :
every job...
2026-10-02 21:22:25
5
Orange Carmona :
The fault current study has nothing to do with what sparky blew up. Sparky should have megged his wires before turning the breaker on and verified torque settings. If he pulled his wires based of what the engineer put on the drawing, it’s not his fault. Sparky, don’t clean up your trash, that’s the GC’s job. Unless it’s big copper wire 😂
2026-10-02 21:57:41
0
🥓Orkin🥓 :
the coordination study is always wrong. sometimes it is just a naming convention wrong, sometimes you think the engineers were high when they made it.
2026-10-02 22:55:27
0
Ambatson88 :
Free money is what that is! Approved submittals is all I got to say.
2026-10-02 20:53:05
1
cc_oklahoma_prepper :
most jobs i run im the hvac and plumg forman in one lol that helps alot then i know quite about about elc codes lol
2026-10-02 22:57:53
0
XT :
Change orders!! And I guess this is based off plans and spec bids, not design build. Also, a good EC would have caught this during pathways.
2026-10-02 23:37:49
0
Pepi :
Just happened to me - mechanical contractor substituted the units and never sent us the updated submittals.
2026-10-03 00:09:01
0
anadate kanadate :
Just had a submittal approved on a gear package "as noted". The note: Nothing is to be ordered until they send in a notorized letter with proof, stating that an onsite meeting between the mech, elect, plumb ect.. and that all MOP & MOCP has happened.
2026-10-02 22:55:12
0
seanchmelyk7 :
how is every one of your videos so spot on!
2026-10-02 21:12:36
0
osiel239101 :
Had this happen before 😂 plans called for 3phase air handlers and single phase air handlers were installed. HVAC had to swap units and we had to pulled new wires and redo panels, big damn mess
2026-10-02 22:33:15
0
VineIterum :
So we don’t have approved submittals?
2026-10-02 22:03:36
0
JPW 🇺🇸 :
This retired electrician is laughing his head off
2026-10-02 22:49:21
0
ticktokpass :
As a retired Plumber, I’m on his side open the window if it gets hot !
2026-10-02 21:49:43
0
Dan :
Why is this such a problem on every job. What’s the point of submittals if the architect and engineer don’t actually follow up with the design changes.
2026-10-02 23:38:37
0