@engineersdesign: Pile Cap Concrete After Cofferdam Dewatering After dewatering cofferdam, pile cap concreting begins. Process: Check dry bed, pile cutoff level, 75mm lean concrete, formwork & steel fixing, then M25-M35 concrete with tremie/pump, full compaction & 7-day curing. Key step for bridge & deep foundation stability. Dewatering pumps must stay ON during pour. #PileCapConcreting #CofferdamDewatering #BridgeConstruction #CivilEngineering #foryou