@architecthansel: BOQ 1. 6INCHES BLOCKS = 4469 2.CEMENT =550 BAGS 3.ROUGH SAND =2TRIP 4.SMOTHE SAND=3TRIP 5.QUARRY STONE = 4 AND 1/2 TRIP IRON ROD 1.12MM HIGH TENSILS(40FT):80PCS 2. 16MM HIGH TENSILS(40FT):52PCS 3. 8MM HIGH TENSILS(30FT/40FT): 193 PCS 4. BINDING WIRE: 2 ROLLS + 1OKG NAILS ROOFING SHEET 7 BUNDLES WINDOW AND DOORS 1. 8 units of 3feet doors 2. 4 units of 2.5feet toilet and bath doors 3. 1 units 4feet double door 4. 10 units of 5feet by 5feet windows 5. 4 units of 2.5 by 2.5feet windows for toilet and bath plus one visitor washroom 6. 1 units of 7feet by 5feet window plumbing,electrical,tieling and finishing 260k foundation to lintel 150k roofing plus block work including workmanship 180k this is a rough estimate +233591069778